New Floating Bridge – Build Update

The photographs were taken during a routine project update meeting on 24 May.

They show the superstructure which now includes the hull, car deck and both chain troughs.

Over the next two weeks all of the welding to this phase will be completed with work then commencing on both the passenger accommodation and the drive systems.